Concrete work continues as footers and Garage P4 level columns are poured. Other ongoing work includes waterproofing the walls in front of the sheeting and shoring, installing the below- grade storm water tanks and removing rock and soil under the east elevation shoring system.
The second tower crane pad has been poured in the north/northeast quadrant of the site. The tower crane itself will be installed the first week of June. Excavation has begun on the construction ramp. Excavation is expected to be completed by July.