The following will be repaved, taking three to four weeks, depending on weather conditions:
- Peachwood Subdivision, Silver Spring, began the week of July 16.
- Hoyles Addition, Gaithersburg, began in late July.
- South Four Corners, Kemp Mill, will begin in August.
- Medical Center Drive from Great Seneca Highway to Key West Avenue will begin in August.
- Bells Mill Road, Potomac, began the week of July 22 and will take one to two weeks to complete.
- Edson Lane, Rockville, began July 16 and will take one to two weeks to complete.
- Mahan Road and Ferrara Drive, Wheaton, began the week of July 23 and will take three to four weeks to complete.
- Heathfield Road, Marianna Drive and Parkland Drive, Aspen Hill, will begin in early August.
- Parkland Drive from Chesterfield Road to Aspen Hill Road began the week of July 23.
- Mariana Drive from Parkland Drive to Bauer Drive will begin the week of August 7.
- Franklin Knolls, Silver Spring, which began in early July and should be completed by Fall 2013.
- Kingswell Community, Wheaton, which began in July and will take six to eight weeks to complete.